Lift-Database » Lifts in the world
24-DLM Gaislachkoglbahn
Valley station
Mountain station
Middle station
General information | |
---|---|
Place | Soelden |
resort | ?? |
Region | Tyrol |
Country | |
Name of lift | Gaislachkoglbahn |
Type | 24-DLM |
Lift manufacturer | Doppelmayr |
Year of construction | 1987/88 |
Commissioning date | 1988 |
Date of closing down | 19/04/10 |
Date of pull down | 19/04/10 |
Infos for handicapped persons |
---|
Sorry, no information available. |
Characteristics |
---|
The mother of all funitels. 2 Sections. This was the only type of this cabelcar (DLM-function) on the world. |
geometric data | |
---|---|
Height of valley station | 1370 m |
Height of middle station(s) | 2178 m |
Height of mountain station | 3041 m |
Vertical rise | 808 / 863 m |
Route distance | 2048 / 1981 m |
Horizontal length | 1837 / 1721 m |
Average incline | 45,90 % |
Largest incline | 76,00 % |
Number of pillars | 7/5 Stk |
Greatest spanwidth | 860 m |
Max ground clearance | ?? m |
Trackwidth drive | 5,0 m |
Trackwidth line | 6,0 m |
Trackwidth return | 6,2 m |
Angle of wrap (drive wheel) | ?? ° |
Drive altitude of site | ?? m |
Maximum capacity | 2600 / 1250 Pers/h |
Travel time | 6 / 6 min |
Driving speed line | 6,0 m/s |
Driving speed station | ?? m/s |
electrical data | |
---|---|
Electrical control | Elin |
Remote control and telemonitoring system | ?? |
Power control system | ?? |
Number of drive | 4 Stk |
Drive power (Start) | 3590 kW |
Drive power (Operation) | 2300 kW |
Brake power | ?? kW |
Continuous brake power | ?? kW |
Driving station | Valley station |
Drive type | electrical |
Traction of drive | electromechanical |
Emergency drive | diesel engine |
Traction of emergency drive | ?? |
cabins data | |
---|---|
Grip type | ?? |
Cab manufacturer | CWA |
Cab model | ?? |
Seating | none |
Seat heater | no |
Heater | no |
Aircon | no |
Persons per cab | 24 |
Number of cabs | 38 Stk |
Cab distance | ?? m |
Cab interval | ?? s |
Garage type | ground floor |
Garage place | Middle station(s) |
Garage direction | forward |
Loading direction | forward |
rope data | |
---|---|
Rope manufacturer | Fatzer |
Length of haul rope | 16350 m |
Total weight of haul rope | 170 t |
Haul rope diameter | 52 mm |
Nominal strength of haul rope | ?? N/mm² |
Breaking strength of rope | ?? kN |
Tensionstation haulrope | Mountain station |
Tension type | hydraulical (controlled) |
Tension way | 17 m |
miscellaneous data | |
---|---|
Transport uphill | 100 % |
Transport downhill | 100 % |
Drive direction | right |
Construction costs | ?? ATS |
Currency (Construction costs) | Austrian schilling |
Construction period | 24 months |
Seasontime | ❄ ☀ all-season |
Evacuation ropeway | no |
Integrated rescue system | no |
Asset number (Trail map) | ?? |
Updates
Datas: 26/06/22
PHOTOS: ??
Lift-Statistics
57523 visit(s) since 20/11/02
Last visit 16/11/24
LIFT-WORLD IDs
Lift-ID: 1
Place-ID: 1
https://www.seilbahntechnik.net/en/lifts/1/datas.htm
Datas: 26/06/22
PHOTOS: ??
Lift-Statistics
57523 visit(s) since 20/11/02
Last visit 16/11/24
LIFT-WORLD IDs
Lift-ID: 1
Place-ID: 1
https://www.seilbahntechnik.net/en/lifts/1/datas.htm