Lift-Database » Lifts in the world
4-CLD/B Sendleitenbahn
General information | |
---|---|
Place | Bad Hofgastein |
resort | ?? |
Region | Salzburg |
Country | |
Name of lift | Sendleitenbahn |
Type | 4-CLD/B |
Lift manufacturer | Girak |
Year of construction | 1992 |
Commissioning date | ?? |
Infos for handicapped persons |
---|
Sorry, no information available. |
Characteristics |
---|
nothing |
geometric data | |
---|---|
Height of valley station | 1558 m |
Height of mountain station | 2019 m |
Vertical rise | 462 m |
Route distance | 1283 m |
Horizontal length | 1197 m |
Average incline | 38,57 % |
Largest incline | 70,54 % |
Number of pillars | 13 Stk |
Greatest spanwidth | ?? m |
Max ground clearance | ?? m |
Trackwidth drive | ?? m |
Trackwidth line | 4,8 m |
Trackwidth return | ?? m |
Angle of wrap (drive wheel) | ?? ° |
Drive altitude of site | ?? m |
Maximum capacity | 2215 Pers/h |
Travel time | 4,9 min |
Driving speed line | 4,5 m/s |
Driving speed station | ?? m/s |
electrical data | |
---|---|
Electrical control | Doppelmayr |
Remote control and telemonitoring system | ?? |
Power control system | ?? |
Number of drive | ?? Stk |
Drive power (Start) | ?? kW |
Drive power (Operation) | 435 kW |
Brake power | ?? kW |
Continuous brake power | ?? kW |
Driving station | Mountain station |
Drive type | electrical |
Traction of drive | ?? |
Emergency drive | ?? |
Traction of emergency drive | ?? |
cabins data | |
---|---|
Grip type | Nockenklemme Typ A |
Cab manufacturer | Girak |
Cab model | ?? |
Bubble colour | neutral |
Seating | Icolan |
Seat heater | no |
Persons per cab | 4 |
Number of cabs | 98 Stk |
Cab distance | 29,25 m |
Cab interval | 6,5 s |
Garage type | underground |
Garage place | valley station |
Garage direction | backward |
Loading direction | forward |
rope data | |
---|---|
Rope manufacturer | Austria Draht |
Length of haul rope | ?? m |
Total weight of haul rope | ?? t |
Haul rope diameter | 38 mm |
Nominal strength of haul rope | ?? N/mm² |
Breaking strength of rope | ?? kN |
Tensionstation haulrope | Valley station |
Tension type | hydraulical (controlled) |
Tension way | ?? m |
miscellaneous data | |
---|---|
Transport uphill | 100 % |
Transport downhill | ?? % |
Drive direction | left |
Construction costs | ?? ATS |
Currency (Construction costs) | Austrian schilling |
Construction period | ?? months |
Seasontime | ❄ winter |
Situation of entrance | parallel |
Situation of exit | parallel |
Loading carpet | no |
Evacuation ropeway | no |
Integrated rescue system | no |
Rope position control | ?? |
Asset number (Trail map) | ?? |
Updates
Datas: 16/02/24
PHOTOS: ??
Lift-Statistics
21755 visit(s) since 09/08/03
Last visit 15/11/24
LIFT-WORLD IDs
Lift-ID: 2432
Place-ID: 245
https://www.seilbahntechnik.net/en/lifts/2432/datas.htm
Datas: 16/02/24
PHOTOS: ??
Lift-Statistics
21755 visit(s) since 09/08/03
Last visit 15/11/24
LIFT-WORLD IDs
Lift-ID: 2432
Place-ID: 245
https://www.seilbahntechnik.net/en/lifts/2432/datas.htm