Lift-World.info
Lifttechniek beweegt ons!
☰ Menü
Lift database
Lift database
Wereldkaart
Wereldkaart
Nieuwe liften
Lift in bouw
Liftprojecten
Uitgebreid zoeken
Geolocation search
Statistiek
Wissen & Techniek
Wissen & Techniek
Bouwvoortgang
Documentaires
Forum
Ledenruimte
Ledenruimte
Login
Wachtwoord vergeten?
Registratie
Aervice
Aervice
Buy a lift:
- New lifts
- Internet stock exchange
Nieuws
RSS-Feeds
Links
Contact
Helpt u ons
Disclaimer
Cookie Policy
Privacy Policy
Terms of use
Impressum
NL
Deutsch
English
Français
Italiano
Česky
Nederlands
Information Slider
Wissen & Techniek
» Bouwvoortgang
‹ Terug
|
home page
|
overzicht
|
Verder ›
The construction of a 4-seater chairlift :: Pillar assembly
End of July 2004
full screen
Pillar assembly
Have a break!
full screen
Pillar assembly
A pillar yoke.
full screen
Pillar assembly
The first pillars are ready.
In 3 days four men installed 11 pillars completely.
full screen
Pillar assembly
full screen
Pillar assembly
The material ropeway transported the pillar parts to their place of destination.
full screen
Pillar assembly
full screen
Pillar assembly
The both pillar shaft parts will be screwed together.
full screen
Pillar assembly
Source text / photo: © 2004 www.lift-world.info / Markus Opatz